Jamaica Manufacturing Facility — Energy Retrofit
Caribbean Manufacturing Co.
$180K/yr
Cost Savings
45%
Efficiency Gain
18 Months
Payback
Overview
Comprehensive energy audit and retrofit for a 100,000 sq ft manufacturing facility including LED lighting, HVAC optimization, and smart controls.
The Challenge
The facility was consuming over $400,000 annually in electricity with a 100,000 sq ft production floor using outdated metal halide lighting, oversized HVAC units, and no building automation. Production schedules varied significantly, but energy consumption remained constant.
Our Solution
We performed a Level III ASHRAE energy audit, identifying $180K in annual savings opportunities. The retrofit included 850+ LED fixtures with smart dimming, VFD-equipped HVAC optimization, IoT occupancy and temperature sensors across the production floor, and a centralised building management system (BMS) with automated scheduling.
Services Delivered
- Energy Audit
- LED Retrofit
- Smart Controls
Key Outcomes
- Annual energy cost savings of $180,000 (45% reduction)
- Full payback achieved in just 18 months
- Lighting energy reduced by 72% with improved visibility on the production floor
- HVAC efficiency improved by 38% through VFD optimization and smart scheduling
- Carbon emissions reduced by 220 tonnes per year